Program

One campaign, one revision, one document

A campaign is scoped by stress family and by unit revision. We do not run mixed revisions on a shared fixture, because the margin numbers stop being comparable the moment two builds share a baseline.

StageDurationOutputCustomer input
Intake2–3 days Fixture plan, stimulus script, unit log Production-intent units, mounting intent, duty cycle
Instrument1–2 days Channel map, baseline traces Confirmation of the channels that matter
Run3–10 days Live telemetry, raw logs None — the run does not depend on attendance
Triage2 days Failure list with reproduction rate Access to the design owner for the failure review
Report5 working days Failure-first report, margin table, traces None
Deliverables

What lands in your inbox

01

Failure list

Every anomaly, ordered by reproduction rate, with the channel and the stimulus phase that exposed it. No item is dropped for being inconvenient.

02

Margin table

Per stress family: the applied level, the first-failure level, and the residual margin in the units you intend to ship.

03

Raw traces

CSV per channel plus the bench script, so an engineer who was not in the room can re-derive every number in the report.

04

Containment recommendation

For each failure: design change, screening step, or accepted risk with a stated basis. Ranked by cost against effect.

05

Fixture record

Fixture drawing and mounting notes, retained for the revision ladder so a follow-up round reuses the same mechanical boundary.

06

Baseline archive

Traces and scripts for this revision, kept for 24 months, so the next comparison is against the same data rather than a fresh guess.

Scheduling

Bench hours and lead time

Quoted in bench hours, not in calendar days. A thermal campaign and a shock campaign of the same "week" are not the same amount of work.

  • Lead time2–3 weeks from fixture approval to first stimulus
  • Minimum campaign24 bench hours across one stress family
  • Revision ladderSame fixture, 12 bench hours per follow-up revision
  • Concurrent unitsUp to 8 instrumented units per chamber run
  • RetestWithin 30 days of report, at the marginal bench-hour rate
  • Slot horizonPublished three months out; hold requests accepted weekly
Dwell time is not negotiable. A thermal cycle shortened to fit a calendar does not produce a shorter failure — it produces a failure that shows up in the field instead. We will decline a schedule that requires it.